Section 58

A section 58 restriction prevents statutory undertakers from digging up the road for a period of between one to five years after the road has been resurfaced or reconstructed, unless the work is an emergency or needed to provide a new customer connection.

Exempt Work

Works which are exempt:

  • Minor works that do not involve breaking up or excavating in the highway.
  • Immediate works for urgent or emergency purposes
  • Customer connections
  • Works to comply with either improvement notice or prohibition notice issued by the Health and Safety Executive under sections 21 or 22 of the Health and Safety at Work Act 1974.

If the proposed works does not fall within the exempt categories, they may still be able to go ahead. Approval from the authority will be required. Please email roadworks@sthelens.gov.uk giving information about the proposed works.

At present the following Section 38 restrictions apply:

ROAD NAMEWARDSTATUSRESTRICTION START DATERESTRICTION END DATEEXTENT TREATMENT
BILLINGE ROADBILLINGE & SENELEY GREENIn force21/08/202520/08/2027Part of the roadCARRIAGEWAY RESURFACING
BIRCHLEY ROADBILLINGE & SENELEY GREENIn force12/06/202611/06/2029Part of the roadFOOTWAY RESURFACING
CAMP ROADBILLINGE & SENELEY GREENIn force03/06/202602/06/2029Part of the roadCARRIAGEWAY RESURFACING
GARSWOOD ROADBILLINGE & SENELEY GREENIn force13/08/202512/08/2027Part of the roadCARRIAGEWAY RESURFACING
LOW BANK ROADBILLINGE & SENELEY GREENIn force03/06/202602/06/2029Whole roadCARRIAGEWAY RESURFACING
MAIN STREETBILLINGE & SENELEY GREENIn force18/08/202517/08/2027Part of the roadCARRIAGEWAY RESURFACING
MONTREY CRESCENTBILLINGE & SENELEY GREENIn force23/12/202522/12/2028Part of the roadFOOTWAY RESURFACING
RAINFORD ROADBILLINGE & SENELEY GREENIn force16/08/202515/08/2027Part of the roadCARRIAGEWAY RESURFACING
SPINDLE HILLOCKBILLINGE & SENELEY GREENIn force03/06/202602/06/2029Part of the roadCARRIAGEWAY RESURFACING
TITHEBARN ROADBILLINGE & SENELEY GREENIn force13/08/202512/08/2027Part of the roadCARRIAGEWAY RESURFACING
CLIPSLEY LANEBLACKBROOK In force21/06/202620/06/2029Part of the roadCARRIAGEWAY RESURFACING
VICARAGE ROADBLACKBROOK In force21/06/202620/06/2029Part of the roadCARRIAGEWAY RESURFACING
WEST END ROADBLACKBROOK In force21/06/202620/06/2029Part of the roadCARRIAGEWAY RESURFACING
ALFORD AVENUEBOLD & LEA GREENIn force20/01/202619/01/2029Whole roadCARRIAGEWAY RESURFACING
BODDEN STREETBOLD & LEA GREENIn force14/01/202713/01/2030Whole roadCARRIAGEWAY RESURFACING
BUDWORTH AVENUEBOLD & LEA GREENIn force20/01/202619/01/2029Whole roadCARRIAGEWAY RESURFACING
BURNAGE AVENUEBOLD & LEA GREENIn force14/01/202713/01/2030Part of the roadCARRIAGEWAY RESURFACING
CLOCK FACE ROADBOLD & LEA GREENIn force24/04/202623/04/2029Part of the roadCARRIAGEWAY RESURFACING
FINGER HOUSE LANEBOLD & LEA GREENIn force24/07/202622/01/2027Whole roadCARRIAGEWAY RESURFACING
FOREST ROADBOLD & LEA GREENIn force21/09/202520/09/2027Whole roadCARRIAGEWAY RESURFACING
GORSEY LANEBOLD & LEA GREENProposed18/07/202616/01/2027Part of the roadCARRIAGEWAY RESURFACING
LEACH LANEBOLD & LEA GREENIn force24/04/202623/04/2029Part of the roadCARRIAGEWAY RESURFACING
LOWFIELD LANEBOLD & LEA GREENIn force01/09/202531/08/2028Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
MARYLEBONE AVENUEBOLD & LEA GREENIn force09/02/202608/02/2029Part of the roadCARRIAGEWAY RESURFACING
NEILLS ROADBOLD & LEA GREENProposed18/07/202616/01/2027Whole roadCARRIAGEWAY RESURFACING
POLLITT CRESCENTBOLD & LEA GREENIn force26/01/202625/01/2029Whole roadCARRIAGEWAY RESURFACING
TARVIN CLOSEBOLD & LEA GREENIn force20/01/202619/01/2029Whole roadCARRIAGEWAY RESURFACING
TENNYSON STREETBOLD & LEA GREENIn force24/07/202623/07/2029Whole roadCARRIAGEWAY RESURFACING
TIBBS CROSS LANEBOLD & LEA GREENIn force24/07/202622/01/2027Whole roadCARRIAGEWAY RESURFACING
UNION BANK LANEBOLD & LEA GREENIn force24/07/202622/01/2027Part of the roadCARRIAGEWAY RESURFACING
WALKERS LANEBOLD & LEA GREENIn force29/01/202628/01/2029Part of the roadCARRIAGEWAY RESURFACING
BROOKHOUSE GROVEECCLESTONIn force09/02/202608/02/2029Whole roadCARRIAGEWAY RESURFACING
ECCLESFIELD ROADECCLESTONIn force19/06/202618/06/2029Part of the roadCARRIAGEWAY RESURFACING
KNOWLES HOUSE AVENUEECCLESTONIn force17/02/202616/02/2029Whole roadCARRIAGEWAY RESURFACING
MILL BROWECCLESTONIn force20/02/202619/02/2029Part of the roadCARRIAGEWAY RESURFACING
OAK TREE ROADECCLESTONIn force27/02/202626/02/2029Whole roadCARRIAGEWAY RESURFACING
OSBORNE ROADECCLESTONIn force06/03/202605/03/2029Whole roadCARRIAGEWAY RESURFACING
PIKE HOUSE ROADECCLESTONIn force13/08/202512/08/2027Whole roadCARRIAGEWAY RESURFACING
WALMESLEY ROADECCLESTONIn force12/06/202611/06/2029Part of the roadCARRIAGEWAY RESURFACING
WALMESLEY ROADECCLESTONIn force07/09/202506/09/2027Whole roadCARRIAGEWAY RESURFACING
HOMESTEAD AVENUEHAYDOCKIn force17/11/202516/11/2027Whole roadCARRIAGEWAY RESURFACING
NORMAN AVENUEHAYDOCKProposed31/03/202630/03/2028Whole roadCARRIAGEWAY RESURFACING
NORTH FLORIDA ROADHAYDOCKIn force16/11/202515/11/2027Whole roadCARRIAGEWAY RESURFACING
ROSE AVENUEHAYDOCKIn force11/06/202610/06/2029Whole roadCARRIAGEWAY RESURFACING
SOUTHWARD ROADHAYDOCKProposed31/03/202630/03/2028Whole roadCARRIAGEWAY RESURFACING
TAYLOR ROADHAYDOCKIn force17/11/202516/11/2027Whole roadCARRIAGEWAY RESURFACING
LINFORD GROVEMOSS BANKIn force12/08/202511/08/2028Whole roadCARRIAGEWAY RESURFACING
RENFREW AVENUEMOSS BANKIn force21/11/202520/11/2027Whole roadCARRIAGEWAY RESURFACING
WASHWAY LANEMOSS BANKIn force17/06/202616/06/2029Part of the roadCARRIAGEWAY RESURFACING
WOODLANDS ROADMOSS BANKIn force08/10/202507/10/2027Whole roadCARRIAGEWAY RESURFACING
HIGH STREETNEWTON EASTIn force15/06/202614/06/2029Part of the roadCARRIAGEWAY RESURFACING
HIGH STREETNEWTON EASTIn force15/06/202614/06/2029Part of the roadCARRIAGEWAY RESURFACING
BRIDGE STREETNEWTON WESTProposed31/03/202630/03/2029Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
CHEMICAL STREETNEWTON WESTProposed31/03/202630/03/2029Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
EARLE STREETNEWTON WESTProposed31/03/202630/03/2029Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
HAYDOCK STREETNEWTON WESTProposed31/03/202630/03/2029Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
MARKET STREETNEWTON WESTIn force18/05/202617/05/2029Part of the roadCARRIAGEWAY RESURFACING
MARKET STREETNEWTON WESTProposed31/03/202630/03/2029Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
OXFORD STREETNEWTON WESTProposed31/03/202630/03/2029Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
QUEEN STREETNEWTON WESTProposed31/03/202630/03/2029Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
STANLEY STREETNEWTON WESTProposed31/03/202630/03/2029Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
ASHCROFT STREETPARRProposed20/06/202619/06/2029Part of the roadCARRIAGEWAY RESURFACING
BROAD OAK ROADPARRIn force11/10/202510/10/2027Whole roadCARRIAGEWAY RESURFACING
HIGNETT AVENUEPARRIn force17/10/202516/10/2027Whole roadCARRIAGEWAY RESURFACING
MCMINNIS AVENUEPARRIn force17/10/202516/10/2027Whole roadCARRIAGEWAY RESURFACING
NEVILLE AVENUEPARRIn force10/04/202609/04/2029Whole roadFOOTWAY RESURFACING
PARR STOCKS ROADPARRProposed20/06/202619/06/2029Part of the roadCARRIAGEWAY RESURFACING
RUDD AVENUEPARRIn force17/10/202516/10/2027Whole roadCARRIAGEWAY RESURFACING
WINSTON AVENUEPARRIn force14/05/202613/05/2029Whole roadFOOTWAY RESURFACING
HIGHER PARR STREETPEASLEY CROSS & FINGERPOSTIn force18/06/202617/06/2029Part of the roadCARRIAGEWAY RESURFACING
MANOR STREETPEASLEY CROSS & FINGERPOSTIn force02/03/202601/03/2029Whole roadCARRIAGEWAY RESURFACING
PARK ROADPEASLEY CROSS & FINGERPOST/ ST HELENS TOWN CENTREIn force17/03/202616/03/2029Part of the roadCARRIAGEWAY RESURFACING
DERBY DRIVERAINFORDIn force22/10/202521/10/2027Whole roadCARRIAGEWAY RESURFACING
HYDES BROWRAINFORDIn force28/08/202527/08/2027Whole roadCARRIAGEWAY RESURFACING
MOSSBOROUGH ROADRAINFORDIn force26/08/202525/08/2027Whole roadCARRIAGEWAY RESURFACING
OLD LANERAINFORDIn force29/05/202628/05/2029Whole roadCARRIAGEWAY RESURFACING
ROSE DRIVERAINFORDIn force24/10/202523/10/2027Whole roadCARRIAGEWAY RESURFACING
ROSE PLACERAINFORDIn force24/10/202523/10/2027Whole roadCARRIAGEWAY RESURFACING
SANDWASH CLOSERAINFORDIn force31/10/202530/10/2027Whole roadCARRIAGEWAY RESURFACING
ST HELENS ROADRAINFORDIn force06/11/202505/11/2027Whole roadCARRIAGEWAY RESURFACING
BISHOPDALE DRIVERAINHILLIn force23/02/202622/02/2029Part of the roadCARRIAGEWAY RESURFACING
BLUNDELLS LANERAINHILLIn force03/02/202602/02/2029Part of the roadCARRIAGEWAY RESURFACING
LAWTON ROADRAINHILLIn force14/08/202513/08/2027Whole roadCARRIAGEWAY RESURFACING
MALHAMDALE AVENUERAINHILLIn force23/02/202622/02/2029Whole roadCARRIAGEWAY RESURFACING
MILLOM AVENUERAINHILLIn force12/02/202611/02/2029Whole roadCARRIAGEWAY RESURFACING
MOSSDALE DRIVERAINHILLIn force10/02/202609/02/2029Part of the roadFOOTWAY RESURFACING
RAINHILL STOOPS ROUNDABOUTRAINHILLProposed30/10/202629/10/2029Part of the roadCARRIAGEWAY RESURFACING
WARRINGTON ROADRAINHILLIn force19/06/202618/06/2029Part of the roadCARRIAGEWAY RESURFACING
WARRINGTON ROADRAINHILLIn force21/02/202620/02/2029Part of the roadCARRIAGEWAY RESURFACING
WHARFEDALE DRIVERAINHILLIn force10/02/202609/02/2029Whole roadFOOTWAY RESURFACING
BOROUGH ROADST HELENS TOWN CENTREIn force09/03/202608/03/2029Part of the roadCARRIAGEWAY RESURFACING
BURTONHEAD ROADST HELENS TOWN CENTREIn force21/09/202520/09/2027Whole roadCARRIAGEWAY RESURFACING
CLAUGHTON STREETST HELENS TOWN CENTREIn force29/06/202628/06/2029Part of the roadCARRIAGEWAY RESURFACING
STANDISH STREETST HELENS TOWN CENTREIn force20/03/202619/03/2029Part of the roadCARRIAGEWAY RESURFACING
CORPORATION STREETST HELENS TOWN CENTREProposed11/07/202610/07/2029Part of the roadCARRIAGEWAY & FOOTWAY RESURFACING
MILL LANESUTTON LEACHIn force14/12/202513/12/2027Whole roadCARRIAGEWAY RESURFACING
MEADOWCROFTSUTTON NORTH WESTIn force27/02/202626/02/2029Whole roadCARRIAGEWAY RESURFACING
MILL LANESUTTON NORTH WEST/ SUTTON SOUTH EASTProposed20/06/202619/06/2029Part of the roadCARRIAGEWAY RESURFACING
CECIL STREETSUTTON SOUTH EASTIn force05/03/202604/03/2029Part of the roadCARRIAGEWAY RESURFACING
ORVILLE STREETSUTTON SOUTH EASTIn force27/02/202626/02/2029Whole roadCARRIAGEWAY RESURFACING
ADELAIDE AVENUETHATTO HEATHIn force21/05/202620/05/2029Part of the roadCARRIAGEWAY RESURFACING
CANBERRA AVENUETHATTO HEATHIn force21/05/202620/05/2029Part of the roadCARRIAGEWAY RESURFACING
ELTON HEAD ROADTHATTO HEATHProposed18/07/202617/07/2029Part of the roadCARRIAGEWAY & FOOTWAY RESURFACING
ELTON HEAD ROADTHATTO HEATHIn force01/09/202531/08/2028Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
NUTGROVE ROADTHATTO HEATHIn force20/02/202619/02/2029Part of the roadCARRIAGEWAY RESURFACING
SHERDLEY ROADTHATTO HEATHProposed18/07/202617/07/2029Part of the roadCARRIAGEWAY, CYCLEWAY & FOOTWAY RESURFACING
SHERDLEY ROADTHATTO HEATHIn force01/09/202531/08/2028Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
SUTTON HEATH ROADTHATTO HEATHIn force01/09/202531/08/2028Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
KNOWSLEY ROADWEST PARKIn force23/03/202622/03/2029Part of the roadCARRIAGEWAY RESURFACING
KNOWSLEY ROADWEST PARKIn force28/09/202527/09/2027Whole roadCARRIAGEWAY RESURFACING
OLIVER ROADWEST PARKIn force05/06/202604/06/2029Part of the roadCARRIAGEWAY RESURFACING
BISHOP ROADWINDLEIn force02/04/202601/04/2028Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
CANTERBURY STREETWINDLEIn force22/05/202621/05/2029Part of the roadCARRIAGEWAY RESURFACING
CITY ROADWINDLEIn force17/06/202616/06/2029Part of the roadCARRIAGEWAY RESURFACING
COWLEY HILL LANEWINDLEIn force02/04/202601/04/2028Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
GAMBLE AVENUEWINDLEIn force02/04/202601/04/2028Whole roadCARRIAGEWAY & FOOTWAY RESURFACING
RIVINGTON ROADWINDLEIn force10/04/202609/04/2029Part of the roadCARRIAGEWAY RESURFACING
SWINBURNE ROADWINDLEIn force27/11/202526/11/2027Whole roadCARRIAGEWAY RESURFACING

 

 

 